Dasu dam pit excavation to finish by January 2026

September 27, 2025
in Business
Dasu dam pit excavation to finish by January 2026
Share on FacebookShare on TwitterWhatsapp

LAHORE: Excavation of the main dam pit (foundation) area of the Dasu Hydropower Project will be completed in January 2026, followed by the roller-compact-concrete (RCC) trial, to be completed in the next two to three months; subsequently, RCC works on the main dam will start during the second quarter of 2026.

Water and Power Development Authority (WAPDA) Chairman Lt-Gen Muhammad (retd) Saeed was briefed during his visit to the construction of the Dasu Hydropower project, said WAPDA on Friday. The Dasu Hydropower Project GM/PD and project managers of the consultants and the contractors were also present on this occasion.

The WAPDA Chairman reviewed construction progress on key work fronts, including the main dam pit area, crushing and batching plants, power house and transformer caverns, Logro tunnel and Barseen Bridge of the relocated Karakorum Highway (RKKH-1).

During on-site briefings, the Chairman was apprised that construction activities are in progress on 20 work fronts side by side. A number of major milestones have already been achieved, which include the river diversion system, excavation of the main switch yard for the 765 KV transmission line, excavation of the right and left abutments of the main dam, the project colony (phase A) and land acquisition.

It was further briefed that excavation works of the underground power house are scheduled to be completed in February 2026, while the 20.4 km-long RKKH-1, comprising seven tunnels and three bridges, is nearing completion and will be opened for traffic by June 2026. WAPDA is constructing RKKH in the project area as part of the Dasu Hydropower Project and in accordance with the CPEC standards.

WAPDA is also implementing a local area development programme, comprising 69 schemes of infrastructure and public health worth billions of rupees for the socio-economic empowerment of the local populace. Of these, 28 schemes have so far been completed, while the rest are in progress.

Underlying the significance of the Dasu Hydropower Project for improving the energy mix in favour of clean, green and affordable electricity in the country, the Chairman directed the contractors and consultants with an intent to make up for time lost due to security and law and order issues to accelerate construction work.

All stakeholders working on the project emphasised the critical role of local administration and police in ensuring continuity of work at all sites, which was frequently disrupted by protests and roadblocks.

The Chairman also inaugurated the arch portion of Barseen Bridge, which is the longest arch bridge in Pakistan. Security arrangements in the project area were also reviewed in detail during the visit.

It may be noted that the 4320 MW-Dasu Hydropower Project is planned for completion in two stages. At present, WAPDA is constructing stage-1 with an installed capacity of 2160 MW and an annual generation of 12 billion units of low-cost and environment-friendly electricity. The World Bank is providing financial assistance worth US $1.57 billion for stage 1, which is likely to start electricity generation in December 2027.

The stage-2, when implemented, will also provide 9 billion units per annum to the national grid. On completion of both stages, Dasu will become the project with the highest annual energy generation in Pakistan, i.e., 21 billion units on average.

Copyright media, 2025

Share15Tweet10Send
Previous Post

Indian police detain activist after deadly Ladakh protests

Next Post

Deutsche Börse Platform: PSX launches EOD market data product

Related Posts

Global LNG: Asia spot prices at fresh two-month low as mild weather softens demand
Business

Global LNG: Asia spot prices at fresh two-month low as mild weather softens demand

December 5, 2025
Palm rises on Dalian strength, posts second weekly gains
Business

Palm rises on Dalian strength, posts second weekly gains

December 6, 2025
Bullish momentum at bourse, KSE-100 gains over 1,100 points in early trade
Business

Bullish momentum at bourse, KSE-100 gains nearly 900 points during intra-day

December 5, 2025
World’s top solar maker says local manufacturing not yet viable in Pakistan
Business

World’s top solar maker says local manufacturing not yet viable in Pakistan

December 5, 2025
US stocks lower after mixed jobs data
Business

US stocks lower after mixed jobs data

December 4, 2025
Saudi Arabia extends term for $3bn deposit placed with Pakistan for another year
Business

Saudi Arabia extends term for $3bn deposit placed with Pakistan for another year

December 4, 2025

Popular Post

  • FRSHAR Mail

    FRSHAR Mail set to redefine secure communication, data privacy

    126 shares
    Share 50 Tweet 32
  • How to avoid buyer’s remorse when raising venture capital

    33 shares
    Share 337 Tweet 211
  • Microsoft to pay off cloud industry group to end EU antitrust complaint

    54 shares
    Share 22 Tweet 14
  • Capacity utilisation of Pakistan’s cement industry drops to lowest on record

    48 shares
    Share 19 Tweet 12
  • SingTel annual profit more than halves on $2.3bn impairment charge

    47 shares
    Share 19 Tweet 12
American Dollar Exchange Rate
  • Advertise
  • Contact Us
  • Daily The Business
  • Privacy Policy
Write us: info@dailythebusiness.com

© 2021 Daily The Business

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In

Add New Playlist

No Result
View All Result
  • Advertise
  • Contact Us
  • Daily The Business
  • Privacy Policy

© 2021 Daily The Business

This website uses cookies. By continuing to use this website you are giving consent to cookies being used. Visit our Privacy and Cookie Policy.